FGT Critical Notice

Notice ID: 63156
Notice Type: Planned Service Outage
Critical: Y
Notice Status Description: Initiate
Reqrd Rsp Desc: No Response Required
Posting Date/Time: Apr 21 2026 1:17 PM
Subject: MAY 2026 --- FGT ZONES 2 AND 3 MAINTENANCE
Notice Effective Date/Time: May 1 2026 9:00 AM
Notice End Date/Time: Jun 1 2026 9:00 AM
Notice Text:

FGT will be performing maintenance at FGT Compressor Station 8. This maintenance will start May 4, 2026, and is to be completed by the end of gas day May 10, 2026. During this maintenance FGT may continue to schedule up to 1,000,000 MMBtu/day through Station 8. During normal operations, FGT schedules up to 1,075,000 MMBtu/day through Station 8.

FGT will be performing maintenance at FGT Compressor Station 9. This maintenance will start May 1, 2026, and is to be completed by the end of gas May 10, 2026. During this maintenance FGT may schedule up to 1,150,000 MMBtu/day through Station 9. During normal operations, FGT schedules up to 1,250,000 MMBtu/day through Station 9.